How to price a paver patio: a worked example

A step-by-step way to price a paver patio from your own costs: measuring, base, pavers, labor, equipment, overhead and margin, with every number worked through.

JobEasy · Published November 12, 2026

Most paver jobs that lose money don't lose it on the pavers. They lose it on the base nobody priced properly, the extra day the crew spent cutting, or the dump fees nobody remembered. This guide walks through one way to build a patio price from your own numbers, line by line, so nothing gets left out.

The figures below are an example, not market prices. Material and labor costs vary a lot by region and supplier. Put your own costs into the same steps.

Step 1: Measure the area and add waste

Measure the patio as simple shapes: rectangles, triangles and circles. Add them up for the total square footage.

Example: a 16 ft by 20 ft rectangle with a 4 ft by 8 ft step-out.

•Main area: 16 × 20 = 320 sq ft
•Step-out: 4 × 8 = 32 sq ft
•Total: 352 sq ft

Pavers need a waste allowance for cuts and breakage. A straight rectangle with a simple pattern needs less; curves, herringbone and lots of borders need more. Use the figure your own jobs have shown you. In this example we allow 8%:

•352 × 1.08 = 380 sq ft of pavers to order

Measure the edge as well. You'll need it for edge restraint and for any border course.

•Perimeter (roughly): 16 + 20 + 16 + 20 + 8 = 80 linear ft

Step 2: Price the base

The base is where patios fail and where quotes go wrong. Work out the excavation depth from your base spec: base depth plus bedding sand plus paver thickness, below finished grade.

Example spec for a patio with foot traffic: 4 in of compacted base, 1 in of bedding sand, and a 2⅜ in paver. Use the depth your local conditions and the manufacturer's installation guide call for: clay soil, frost and drainage all change it.

Base volume:

•352 sq ft × (4 ÷ 12) ft = 117 cubic ft
•117 ÷ 27 = 4.3 cubic yards compacted

Base material compacts, so order more than the finished volume. If your supplier sells by the ton, convert using their weight per cubic yard. Say your crushed base runs 1.4 tons per cubic yard and you allow 20% for compaction:

•4.3 × 1.2 × 1.4 = 7.2 tons, so order 8 tons

Bedding sand, at 1 in:

•352 × (1 ÷ 12) = 29 cubic ft = 1.1 cubic yards, so order 1.5 yards

Excavated soil has to go somewhere. Price it now:

•352 sq ft × (7.4 ÷ 12) ft ≈ 217 cubic ft ≈ 8 cubic yards in the ground, more once it is dug and loose

If you haul it off, that is truck trips plus dump fees. If it stays on site, it is still labor to spread.

Step 3: Price the materials

Now put your own costs on each line. Example costs only:

ItemQuantityExample costTotal
Pavers380 sq ft$4.50 / sq ft$1,710
Crushed base8 tons$40 / ton$320
Bedding sand1.5 yd$55 / yd$83
Edge restraint and spikes80 ft$1.75 / ft$140
Polymeric sand6 bags$30 / bag$180
Geotextile fabric1 roll$95$95
Delivery2 loads$85$170
Materials$2,698

Check the polymeric sand coverage on the bag for your joint width and paver size; it varies more than people expect.

Step 4: Price the labor in hours, not in a guess

Break the job into tasks and estimate crew hours for each. Your own past jobs are the best guide; time a few and write it down.

Example for a three-person crew:

•Layout and excavation: 10 crew hours
•Base: place and compact in lifts: 10 crew hours
•Screed sand and lay pavers: 14 crew hours
•Cuts and border: 6 crew hours
•Edge restraint, joint sand, compaction, clean-up: 5 crew hours
•Total: 45 crew hours

Multiply by your real cost per crew hour. That is not just wages: include payroll taxes, workers' comp, and any paid time that isn't on a job. Say your loaded cost is $38 per person-hour:

•45 × $38 = $1,710 labor cost

Step 5: Add equipment and disposal

•Mini excavator or skid steer: 1 day at $350
•Plate compactor: 2 days at $90 = $180
•Saw and blades: $60
•Dump fees: $200
•Equipment and disposal: $790

If you own the equipment, still charge for it. Machines wear out and need replacing, and a job that uses them should pay its share.

Step 6: Overhead, then margin

Add up the direct costs:

•Materials $2,698 + labor $1,710 + equipment and disposal $790 = $5,198

Overhead is everything that keeps the company running but isn't on this job: the truck, insurance, phone, office, software, your own time quoting. A simple way to cover it is to work out what your overhead costs per year, divide by the direct costs you expect to run in a year, and add that percentage to every job. Say it comes to 15%:

•$5,198 × 1.15 = $5,978

Profit comes last, as a margin on the price, not a markup on cost. If you want a 20% margin:

•Price = $5,978 ÷ (1 − 0.20) = $7,472

Round it to something clean, like $7,475. A markup of 20% would only give you about 17% margin, which is why the two get confused and why jobs come in thinner than planned.

Step 7: Sanity-check against price per square foot

•$7,475 ÷ 352 sq ft = $21.24 per sq ft

Compare that with your recent patios. If it is far off, find the line that is different. It is usually access, depth, cuts or haul-off, and it should be on the quote so the customer can see why.

What to put on the quote

A customer compares your number with someone else's. Make it easy to see what they are getting:

•The area and the paver chosen (name, color, pattern)
•The base depth and what it is made of
•Edge restraint and joint sand
•Excavation and whether soil is hauled away
•What is not included (steps, lighting, permits) so there is no argument later
•The deposit and when the rest is due

Common mistakes

•Pricing pavers by the square foot and forgetting the base. The base is often as much work as the pavers.
•No waste allowance, or the same allowance for a rectangle and a curved herringbone.
•Forgetting haul-off and dump fees.
•Using wages instead of loaded labor cost.
•Adding margin as a markup on cost, so the profit comes in lower than you meant.
•Quoting from memory. Keep a price book with your current material and labor costs so every quote starts from the same numbers. That is what JobEasy was built for: the price book lives on your phone, so you can price the job on site while you are still standing on it.

Quick checklist

1.Measure, add up the area, add waste.
2.Work out base depth, volume and tons.
3.Price every material, including delivery.
4.Estimate crew hours per task, times loaded cost.
5.Add equipment and disposal.
6.Add overhead, then margin on the price.
7.Check the price per square foot against your last jobs.
8.Put the base, edge and exclusions on the quote.