Sod looks like an easy job to price. Measure the yard, multiply by a number per square foot, done. But the sod itself is often the smaller part of the cost. Taking out the old lawn, hauling it away, fixing the grade and getting the edges right around beds and walks are where the hours go.

This guide shows how to build a sod quote from its parts, then check it against a per-square-foot number at the end. The numbers below are examples only. Use your own sod price, labor rate and dump fees.

Step 1: Measure the area, piece by piece

Break the lawn into simple shapes: rectangles, triangles, circles. Measure each one and add them up. Subtract beds, walks and anything that won't get sod.

Write down as you go:

•Each area's length and width
•What is there now: old grass, weeds, bare dirt, rock
•Low spots, high spots and anywhere water stands
•How the sprinklers cover the area, and any heads that need raising
•Access: can a pallet and a skid steer or trailer get close, or is it all wheelbarrow work through a side gate?
•Where the old turf and debris will go

If you will be cutting, tilling or grading, have the lines marked first. The Common Ground Alliance, which runs the national 811 service, says anyone who plans to dig should contact 811 a few business days before starting.

Example: a front lawn being replaced.

•Main area: 40 ft × 30 ft = 1,200 sq ft
•Side strip: 50 ft × 10 ft = 500 sq ft
•Less a planting bed inside the lawn: 100 sq ft
•Total to sod: 1,600 sq ft

Step 2: Add waste and count pallets

You will lose sod to cuts around curves, beds, trees and edges, and a few pieces may be broken or dry. Add a waste factor from your own jobs. A simple square yard needs less; a yard full of curves needs more.

Example with 5% waste:

•1,600 × 1.05 = 1,680 sq ft needed

Ask your sod farm or supplier how many square feet a pallet covers for the grass you're ordering. It varies by supplier and by grass, so don't guess. Say your supplier's pallet covers 450 sq ft:

•1,680 ÷ 450 = 3.73, so 4 pallets
•4 × 450 = 1,800 sq ft delivered, about 120 sq ft spare

If the spare is large, you can order part of a pallet if your supplier sells it that way, or use it to patch the customer's other areas as a line item.

Step 3: Price the materials

Example costs only:

ItemQuantityExample costTotal
Sod1,800 sq ft$0.45 / sq ft$810
Topsoil for low spots2 cu yd$45 / yd$90
Sod delivery1$95$95
Materials$995

Leave fertilizer off unless your local extension service tells you otherwise for your area. University of Florida IFAS (Florida-Friendly Landscaping program) advises waiting 30 to 60 days before fertilizing new sod.

Step 4: Estimate the labor

Estimate crew hours for each part of the job, from your own past jobs. Example:

•Cut out the old lawn with a sod cutter: 6 crew hours
•Load and haul the old turf: 4 crew hours
•Grade, fill low spots, rake smooth: 6 crew hours
•Lay 1,600 sq ft of sod: 8 crew hours
•Roll, trim edges, cut around beds and walks: 2 crew hours
•First watering and clean-up: 2 crew hours
•Total: 28 crew hours

Use your loaded cost per person-hour: wages plus payroll taxes, workers' comp and paid time off the job. Say $34:

•28 × $34 = $952

Notice that laying the sod is less than a third of the hours. If you priced only the laying, you would miss most of the job.

Step 5: Equipment and disposal

•Sod cutter rental: $120
•Lawn roller rental: $30
•Dump fee for the old turf: $150
•Total: $300

Old turf with soil attached is heavy. Know what your dump charges by weight or by load before you quote, and whether they take it as green waste.

Step 6: Overhead and margin

•Direct cost: $995 + $952 + $300 = $2,247
•Overhead, say 15%: $2,247 × 1.15 = $2,584.05
•Margin on price, say 20%: $2,584.05 ÷ 0.80 = $3,230.06

Round it to $3,230 or $3,250, whichever fits how you present prices.

Step 7: Check the price per square foot

•$3,230 ÷ 1,600 sq ft = about $2.02 per sq ft, tear-out and haul-off included

Now you can answer "what do you charge a foot?" with a real number for this yard. A yard of bare dirt that only needs a rake and sod would come in lower. A yard with a side-gate-only entrance and a lot of curves would come in higher. The number comes from the job, not the other way around.

Sod is ordered for a specific job and doesn't keep, so take a deposit before you place the order. Our guide on [how much deposit to ask for](/guides/how-much-deposit-should-a-contractor-ask-for) covers how to set it.

Put watering in writing

New sod needs water right away, and the first weeks decide whether it roots. UF/IFAS advises laying sod within 24 hours of delivery and giving it light, frequent waterings for the first two to three weeks, keeping the soil moist but not overly wet, then tapering off once it has rooted.

Most of that watering happens after your crew leaves. Put it on the estimate:

•Who waters, how often and for how long
•That the customer should follow local watering rules, which can limit days and times
•What your warranty covers, if you offer one, and that it depends on the watering being done
•Any sprinkler adjustments you are or are not including

This one section heads off most of the "the grass died" calls.

Show the parts that change the price

List these as their own lines so the customer sees why the price is what it is:

•Removal and haul-off of the old lawn
•Grading and fill
•Sprinkler head adjustments
•Edging or trim around beds
•Extra sod for patching other areas

When the customer wants to save money, they can drop a line item instead of asking you to drop your margin.

Common mistakes

•Pricing only the sod and the laying. Tear-out, hauling and grading are often most of the hours.
•Guessing pallet coverage. Ask the supplier for the grass you're ordering.
•No waste factor. Curves and beds eat sod.
•Forgetting the dump fee. Old turf is heavy, and dumps charge for it.
•Ordering before the deposit is in. Sod can't wait in the yard while a customer thinks it over.
•Leaving watering unspoken. If it isn't written down, the dead patch becomes your problem.
•Quoting from memory. Keep your sod price, delivery, rental and dump fees in a price book so every quote uses today's numbers. JobEasy keeps the price book on your phone, so you can measure the yard and hand over the quote before you leave.

Quick checklist

1.Contact 811 if you will cut, till or grade.
2.Measure each area; subtract beds and walks.
3.Note what's there now, the grade, sprinklers and access.
4.Add waste and count pallets from your supplier's coverage.
5.Price sod, soil and delivery.
6.Estimate crew hours for tear-out, hauling, grading, laying and trim.
7.Add equipment, disposal, overhead and margin.
8.Divide by the square footage to check.
9.Write watering instructions and line items on the estimate.
10.Take the deposit before ordering the sod.